I. GENERAL REQUIREMENTS PAGE
1.1 Authority
1.2 Bonding Requirements
1.3 Insurance Requirements
1.4 Permit Application Requirements
1.5 General Policies
1.6 Road Closures
1.7 Staging of Installation
1.8 Safety and Public Convenience
1.9 Road Changes
1.10 Inspections

II. SPECIFICATIONS
2.1 Quality Control
2.2 Trenching and Backfill
2.3 Compaction Tests
2.4 Resurfacing
2.5 Fees

I. GENERAL REQUIREMENTS

1.1 Authority
1.1.1 Authority for the administration and enforcement of the Fremont County Street Cut Requirements is derived from the Colorado Revised Statutes (C.R.S.), Sections: 30-11-107; 37-84-103; 37-84-106; 38-5-101; 42-4-101 through 42-4-115; 42-4-501 through 42-4-1406; 43-2-111; 43-2-147; 43-5-301; and 43-5-307 and 42-4-512

^ Back to Top ^

1.2 Bonding Requirements
1.2.1 Prior to the issuance of a permit, the excavator, shall have on file with the County Road and Bridge Department, a Permit Bond in the amount of two-thousand ($2,000.00) dollars, unless otherwise specified by the Authorized County Representative. Such Permit Bond shall be for the benefit of Fremont County and shall assure recovery of any expense incurred in replacement of any subsur­face materials or asphalt replacement or any other work which has not been complet­ed in be in force until the Final Acceptance Certificate is issued. The Permit Bond shall not exceed the cost of the project.

1.2.3 If said work and installation are not completed in accordance with these regulations as determined by the Authorized County Representative, said bond shall be in default. The Contractor shall be notified in writing of the deficiencies and will be granted thirty (30) days for corrections, if deficiencies have not been corrected in said period, Permit Bond will be activated. If work is brought to compliance within thirty (30) days, no action will be taken.

^ Back to Top ^

1.3 Insurance Requirements
1.3.1 Prior to the issuance of a permit the excavator shall provide documentation of a current Bodily Injury and Property Damage Liability Insurance Policy, with minimum of one million ($1,000,000.00) dollars combined Single Limit coverage. Such policy shall be for the protection of the County from all suits, actions or claims of any type for injuries or damages allegedly sustained by any person or property on the premises or as a result of the work. Such policy shall specifically cover the acts and operations of any subcon­tractors or independent contractors of the excava­tor, in addition to the excavator and his employees or agents.

^ Back to Top ^

1.4 Permit Application Requirements
1.4.1 The following regulations shall apply to all excavators, including but not limited to any person, contractor, developer, partnership, corporation, limited liability corporation, municipality, special district, or other governmental entity), who for any reason cuts, disturbs, or otherwise defaces any County public right-of-way maintained or not maintained. Excavators shall obtain a “ 30 Day Street Cut Permit” from Fremont County in accordance with these requirements.

1.4.2 The excavator by applying for and obtaining a permit agrees to be liable to the County for any expenses incurred by the County as a result of such excavator's acts or omissions in performing the excavation. In addition, the excavator shall hold the County harmless from any claims arising from or relating to the work. This shall include, but not be limited to, a Warranty by the excavator of the work and all materials and labor used in the work. Such Warranty shall be effective for two (2) years from the issuance of the Prelimi­nary Certificate of Compliance. If further repairs or maintenance are required due to any defect or omission in the completion of the work, the excavator may be required to adequately and properly provide and com­plete any such repairs or maintenance.

1.4.3 The excavator acquiring a permit shall be familiar with and at all times shall observe and comply with all Federal and State laws, local laws, ordinances and regula­tions pertaining to the excavator's work. The excava­tor shall indemnify and hold harmless the County of Fremont, Colorado, and its representatives against any claims arising from any violation of such law, ordinance or regulation; whether by the excavator or by the excavator's employees, independent contractors and subcontractors.

1.4.4 Prior to commencing any work, except the work of adjusting manhole rings and service boxes, the excavator who will actually perform the work shall obtain written permission to undertake said work in accordance with these regulations.

1.4.5 The Street Cut Permit shall be obtained at least five (5) working days, prior to the planned commencement of construction and shall have a specified date for commencement and completion of construction. Exceptions to the Five-day requirement made by the Authorized County Representative.

1.4.6 Permits shall be required for emergency repairs; Excavators must obtain such permit within seventy-two (72) hours following commencement of work. Failure to acquire a permit with­in this specified time shall result in a penalty permit being issued.

1.4.7 The applicant shall submit construction plans, specifications, and a written schedule covering general sequence and staging of the work to be performed, if available. For minor installations, only a sketch is required.

1.4.8 The schedule and the plans shall not be changed after the permit is approved without the written approval of the Authorized County Representative.

1.4.9 Permits shall be available for inspection at the project site at all times.

1.4.10 Any excavator commencing work prior to obtaining a Street Cut Permit, except as provided herein, shall be issued a penalty permit in lieu of the normal permit; and shall be required to pay an additional fee pertaining thereto as provided in the fee schedule herein.

1.4.11 A Street Cut Permit shall not be issued to any excavator who is in non-compliance with any of the provisions of these regulations.

^ Back to Top ^

1.5 General Policies
1.5.1 Work shall be conducted so as not to create safety hazards, maintenance problems or render portions of the right-of-way infeasible for future road improvements.

1.5.2 Plans and profiles for any work affecting grade and alignment shall be submitted to the Authorized County Representative for approval prior to starting any such work.

1.5.3 The excavator shall provide, erect, and maintain all necessary barricades, signs, and illumination devices as required in the "Manual on Uniform Traffic Control Devices" for all work which requires a permit.

1.5.4 In an emergency situation, signing according to the Manual on Uniform Traffic Control Devices shall be required on the project site even though a permit will not be issued until after the excavation has taken place.

1.5.5 Permits issued by the Authorized County Representative per­tain only to work within the County owned or controlled rights-of-way and does not allow entry onto private property adjacent to such rights-of-way, nor does it allow alteration or disturbance of any facilities or installations owned by others that exist within the right-of-way.

1.5.6 All road level accesses (manholes, vaults, etc.), shall be of heavy duty construction, capable of safely supporting anticipated maintenance equipment and vehicular traffic, and shall conform to the finished grade of the road.

1.5.7 All aboveground utilities shall be located and installed to prevent:

1.5.7.1 unnecessary obstruction to pedestrian and vehicular traffic;

1.5.7.2 damage to the utility itself that could be harmful to the general public.

1.5.8 All cuts shall be made with straight boundaries and all cuts shall be within 5 degrees of vertical. In cases where caving or slump of a cut face occurs from under any roadway surfacing, slab or bound type base, the dimensions of the cut shall be extended to the point of occurrence of caving or slump.

No pole or structure aboveground shall be set in conflict with a Pedestrian walkway nor shall it be set less than ten (10) feet from the shoulder of any County road. A minimum ground clearance of 19 feet shall be provided where utility lines cross public roads. The clearance shall be measured from the center of the roadway.

1.5.9 No excavation shall be permitted on any new asphalt, resurfaced or plant mixed sealed, right-of-way that is less than three (3) years old. This provision may be waived at the discretion of the Board of County Commissioners. This provision, however, shall not prohibit any emergency repairs that must be per­formed.

1.5.10 Specifications for location of utilities and minimum depth requirements are showin Figure 1.5.11.

^ Back to Top ^

1.6 Road Closures
1.6.1 Road closures are not permitted unless justified on the basis of overall benefit to the general public.

1.6.2 Road closures will be permitted only:

1.6.2.1 If written approval is granted by the Authorized County Representative. Request for approval shall be in writing to the Autho­rized County Representative at the time of permit application. In an emergency written permission will be waived, however, the exca­vator shall notify all agencies listed in 1.6.3.1.

1.6.2.2 Between the hours of 6:00 a.m. and 7:00 p.m.

1.6.3 When road closures are permitted, the excavator shall:

1.6.3.1 At least ten (10) working days prior to beginning work notify the appropriate fire protection district, school district, sheriffs office, of the exact location, date and time of right-of-way closure.

1.6.3.2 Erect and maintain, at excavator's expense, necessary barricades, flashers, construction signs, and flag persons, in accordance with the "Manual On Uniform Traffic Control Devices" and shall take all necessary precautions for public safety and convenience.

^ Back to Top ^

1.7 Staging of Installation
1.7.1 Staging may be required by the Authorized County Representative, to produce the least disruption possible for the traveling public. A permit for any subse­quent stage will not be issued until the prior stage has satisfactorily pro­gressed or been completed.

^ Back to Top ^

1.8 Safety and Public Convenience
1.8.1 The excavator shall at all times conduct work to ensure the least possible obstruction and hazard to the traveling public. The safety and convenience of the gener­al public and the residents along the road and the protection of persons and property shall be insured at all times.

1.8.2 All repairs being made to the street or other County property involved, shall result in the street or property being returned to a condition equal to, or better than the original condition, within the limits of care­ful, diligent workmanship, good planning and quali­ty materials. These repairs must be accomplished in the least possible time and with the least disturbance to the normal function of the street or other property.

1.8.3 Except where trench banks are cut back on a stable slope to prevent caving or sliding, trenches shall be properly and substantially braced, and sheathed where necessary, to prevent caving or sliding. Sheathing shall be supported by means approved by the Occupational Safety and Health Administration (OSHA).

1.8.4 All blasting in connection with the Street Cut Permit shall comply with all laws, ordinances, regulations, and requirements of applicable safety codes relative to the handling, storage and use of explosives and the protection of life and property.

1.8.5 The excavator shall notify all property owners within five hundred feet (500) ft. of the actual blasting site prior to blast­ing.

1.8.6 The excavator will also be strictly liable for all damages caused by his blasting operations. Suitable weighted plank coverings or mattresses shall be provided to confine all materials lifted by blasting within the limits of the excavation or trench.

^ Back to Top ^

1.9 Road Changes
1.9.1 If any changes are made in a County right-of-way that would necessitate the removal or relocation of an installation made by an excavator, or utility, the relocation or removal shall be at the excavator or utility owner's expense upon written request by the County. The relocation or removal shall be completed within thirty (30) days after notification for minor projects. For major utility relocation projects that require extensive design, securing of contracts or material orders, the reloca­tion or removal shall be within ninety (90) days. To avoid the necessity for such changes, the excavator may be required to locate the facility in a manner which is consistent with future plans for the right-of-way in which it is located.

^ Back to Top ^

1.10 Inspections
1.10.1 The Authorized County Representative has the authority to reject defective materials, or inferior materials, defective workmanship and to sus­pend work until such time as the excavator shall correct the situation in question, subject to final deci­sion by the Authorized County Representative.

1.10.2 The excavator shall notify the Authorized County Representative at least twenty-four (24) hours prior to begin­ning any excavation. If work stops on a project during any stage of excavation for a period of more than twenty-four (24) hours, the Authorized County Representative shall be notified at least twenty four (24) hours prior to any resumption of work on the project. If the exca­vator intends to work shifts, double shifts or hours other than the normal workday of Fremont County the excavator shall notify the Authorized County Representative at least twenty-four (24) hours prior to working extraordinary hours, except in the event of an emergency. Failure by the excavator to notify the Autho­rized County Representative as stated above may result in revocation of the original permit and issuance of a penalty permit.

1.10.3 Inspections shall be made as deemed necessary during the construction period by the Authorized County Representative to insure that work is processing in compli­ance with these regulations. Deviation from these regulations will be sufficient reason for shut down orders to be issued by the Authorized County Representative until prop­er corrections and/or ad­justments have been made by the excavator.

1.10.4 Before a pavement section is replaced (patched), the excavator shall notify the Authorized County Representa­tive at least twenty-four (24) hours prior to the date excavation is scheduled to commence. The excavator shall notify the Authorized County Repre­senta­tive when the backfi­ll has been completed. Failure of notifica­tion may result in a demand to have such work redone in order to pass a final inspection.

^ Back to Top ^

II. SPECIFICATIONS

2.1 Quality Control
2.1.1 All work shall conform to the FREMONT COUNTY STREET CUT REQUIREMENTS as outlined in this document.

2.1.2 Any work in which untested and unaccepted materials are used without written approval by the Authorized County Representative shall be removed and replaced at the excavat­or's ex­pense.

2.1.3 Tests ordered by the Authorized County Representative to ascertain compliance with specifications shall be the most recent standard methods of AASHTO or ASTM and shall be made by an independent testing firm at the expense of the exca­vator. Where the excavator or owner maintains his own testing equipment and qualified personnel, the require­ment for an independent testing firm may be waived by the Authorized County Representative. Copies of test data are to be furnished to the Autho­rized County Representative within five (5) working days, of completion of testing.

2.1.4 The excavator shall be fully responsible for the maintenance and correction of any faulty construction, including unsuitable road cuts and chuckholes developed during the construction period. The roadway and roadside areas where work has been performed shall be thor­oughly cleared of all debris and extraneous material and shall be restored to a condition at least as good as the original condition. The Authorized County Rep­resentative shall examine the work area to ensure against inade­quate cleanp of pavement and all roadway appur­tenanc­es; including but not limited to, pavement fail­ures, broken concrete, damaged signs and fencing, debris on adjacent private property. All deficiencies must be resolved to the satisfaction of the Authorized County Representative.

2.1.5 Damaged pavement shall be repaired by appropriate methods as approved by the Authorized County Representative. Cracks are to be filled with the proper asphalt hot bituminous pave­ment product and the surface properly seal-coated. An overlay the full width of the paved surface shall be required for situations when in the opinion of the Authorized County Representative, the riding quali­ty, safety, or the appearance of the finished roadbed has been im­paired. Sub-grade failures caused by the excavator's operation of heavy equipment shall be rectified by reconstructing the sub-grade layers and replacing the sub-base, base, and asphalt pavement.

^ Back to Top ^

2.2 Trenching and Backfill
2.1 All backfill materials, compaction and resurfacing of any excavation made in the County right-of-way will be done in accordance with the following provisions: Back filling and compacting shall begin after first having properly bedded and compacted to a depth of not less than one (1) foot over the top of the structure or utility line being installed or repaired in accordance with the specifications of the person or corporation responsible for the maintenance of the structure or utility line.

2.2.2 Jetting backfill will not be permitted within County roadways.

2.2.3 At no time will contaminated, wet, soggy, frozen or other unsuitable materials be allowed as backfill. If proper backfill material is not at the excavation site, suitable material shall be brought in. All unsuitable materi­al shall be re­moved from the site.

2.2.4 All excavations on the traveled surface of the roadway shall be replaced with flowable fill or with a suitable gravel road base material. Compaction tests are waved when flowable fill is used.

2.2.5 All excavations made in the traveled surface of a graveled roadway shall be replaced with a suitable gravel road base material (as ap­proved by the Authorized County Representative) which shall be com­pacted to a 95% maxi­mum density (AAS­HTO T 180) to the natural road grade.

2.2.6 All excavations made outside of the traveled surface may be replaced with the natural excavated material approved by the Authorized County Representative. If natural excavated material is not acceptable the exca­vation shall be replaced with material as determined by the Authorized County Representative.

2.2.7 All gravel replacement material shall be compacted in lifts of eight (8) to twelve (12) inches.

2.2.8 All cuts made in asphalt streets shall be made by mechani­cally cutting to a true horizontal and vertical line, and shall be cut six (6) inches wider on each side of the trench excavation. The final asphalt cut shall not be made until immediately prior to patch­ing.

2.2.9 All excavations that are made in asphalt streets shall be completely restored within fifteen (15) days after acceptance of the backfill by the Authorized County Representative. In the event weather conditions preclude restoration by permanent hot bituminous pavement, temporary repairs shall be made by tamping and rolling into place a cold mix asphalt. Such cold mix patches shall be removed and replaced by a permanent hot bituminous pavement within thirty (30) days or as weather and availability of materials permit, but in no event shall the replacement shall occur more than six (6) months from the date of patching.

2.2.10 All cuts made in paved streets shall be replaced to a thickness of Four (4) inches of bituminous material.

2.2.11 All underground installations crossing the roadway shall be encased in conduit of a larger diameter.

^ Back to Top ^

2.3 Compaction Tests
2.3.1 All excavations shall be replaced with a suitable gravel road base material (as approved by the Authorized County Representative), and it shall require a compaction test. The excavator shall have the compaction tests conducted by an approved testing laboratory or by alternative qualified testing agencies if approved by the Board of County Commissioners. A copy of the results shall be furnished to the County no later than five (5) days after the test is conducted. Compaction test are waved only with use of flowable fill.

2.3.2 Compaction tests shall be taken on each longi­tudinal and/or each crosscut at intervals as determined by the Authorized County Representative.

2.3.3 Each lift shall be compacted to 95% maximum density (AASHTO T-180) before the next lift is installed. Backfill within twelve (12) inches of finished grade shall consist of three-quarter inch road base, compacted to 95% (AASHTO T-99). In some cases an additional depth of three-quarter inch road base may be requested by the Authorized County Representative.

^ Back to Top ^

2.4 Resurfacing
2.4.1 After proper backfill procedures are completed in accordance with the preceding requirements, the excavator shall notify the Authorized County Representative.

2.4.2 After inspection of the backfill, compaction test and clean-up of the work area the Authorized County Representative will notify the excavator of any deficiencies which shall be corrected by the excavator. The corrections shall be made within fif­teen (15) days following notification..

2.4.3 Required Overlay: Overlay of the entire street width shall be required, when the excavation is made longitudinally within the paved street. In addition the pavement shall be feathered to the natural grade on both ends.

2.4.4 The minimum compacted depth of the Asphaltic Con­crete shall be feathered as much as possible eliminating the fracturing of the mix aggregate. The areas of overlay shall require a tack coat of CSS-1 at the rate of 0.10 gallon per square yard. All overlays shall be placed in good workmanlike manner using standard practices.

^ Back to Top ^

2.5 Fees
STREET CUT PERMIT FEES
One hundred dollars for the first 50 lineal feet; five cents per lineal foot for every additional lineal foot over 50 feet.

UTILITY POLES AND PEDESTALS
Fifty dollars fee for placement of utility poles or pedestals.

ASPHALT REPLACEMENT COSTS
Replacement costs will be based on actual costs at the time of replacement.

ADDITIONAL COSTS
Cost of placing barricades and/or interim repairs required due to failure of the excavator to maintain SAFE conditions will be billed to the excavator. These charges will be based on actual costs.

PENALTY PERMIT FEES
A penalty shall be issued to any excavator commencing work prior to obtaining a Permit (unless exempted). The penalty fee is $500 for the first offense and $1,000 penalty for all other offenses. All fees shall be established from time-to-time by resolution of the Board of County Commissioners.

2.6 VIOLATIONS
In addition to the Penalty Permit Fees set forth above, the county shall be entitled to pursue all available civil remedies to compensate the county for damages done to any rights-of-way.

^ Back to Top ^

NORMAL DEPTHS

GAS-------------------------------------- 48" min.
TELEPHONE-------------------------------40" min.
ELECTRIC POWER-------------------------48" min.
STORM OR SANITARY SEWER-------min. depth determined by Engineer.
CABLE T.V.--------------------------------40" min.
WATER------------------------------------40" min.
FIBER OPTIC (with 1" tracer wire above the line)------------------48" min.
OVERHEAD UTILITIES--------------------------19' from center of roadway